A structured catalogue of 48 project management processes and procedures covering governance, engineering, procurement, construction, commissioning, and operational controls for successful capital project delivery.
Procedure library
48 procedures, each with its document, purpose, and value.
For every process: the key document(s) produced, what the document does, and the value it brings to the project.
#
Document / Process
Explanation & Value
1
Project framework
Defining the scope of the project
Defining and planning the content and scope of the project at each phase of implementation
Gives a clear understanding of what needs to be done and what is not included in the scope of the project
2
Project Execution Plan
Project management
The main document of the project, containing a description of all the work that is required within the framework of the implementation
Gives a clear understanding of what and how it is planned to be implemented
3
Register of design solutions
Decision making
A list of all the main decisions taken on the project
Allows you to record all design decisions
4
Decision Support Package
Decision making
The main document for the management when making decisions on the project
It contains all the data necessary for decision-making
5
Stakeholder management plan
Stakeholder management
Managing stakeholder engagement and expectations
Allows you to identify and work with those parties that affect the project
6
Interfaces Management Plan
Interfaces management
Defines all project interfaces and how to work with them
Allows you to manage all internal and external physical interfaces of all disciplines on the project
7
Communications management plan
Communications management
Defines how the project team will communicate inside and outside the company
Allows you to clearly define the interfaces necessary for communication and responsible
8
Change management plan
Change Management
Sets the procedure for working with changes on the project
Gives a clear understanding of what changes are subject to approval, how they are accepted, recorded, and managed
9
Procedures for document flow, numbering, correspondence management, documentation, and archiving
Document management
Establish rules for numbering, sharing, commenting, using, and archiving documentation
Allow you to restore order in the movement of all types of documents on the project
10
The financial and economic model Budgets Cash flow
Financial management
Structures the cost and revenue parts of the project
Gives an understanding of how much money is needed for each cost item, from which source they will be financed, and what overall financial indicators of the project are planned to be achieved during the execution
11
Project control procedure
Project control
Defines the order of project control, reporting, and its frequency
Allows you to establish a clear understanding of who, how, and when will control the implementation of the project
12
Work breakdown structure
Project structure
Defining the structure of the project work
Creates the basis for the main documents of the project. Defines a clear structure of all documents and works on the project
13
Project scheduling procedure
Project planning
Defines project planning requirements
Allows you to determine what details are required for the project schedule, how it should be formed and used
14
Progress measurement procedure
Progress measurement
Discloses the requirements for measuring the progress of all work on the project
Gives a clear definition of the rules for measuring progress in all disciplines and types of works
15
Project schedule (from 1st to 4th level)
Project schedule
Includes all the work required to be performed on the project
Defines a clear relationship between the work of the entire project, their duration, and criticality
16
Main project milestones
Milestones of the project
Concentrates the project team's attention on the main dates of the project
Determines which stages are key, payment, LD, and require special control
17
Cost assessment report and cost assessment from the 5th to the 2nd classes (according to the ААСE methodology)
Cost estimation
Contains justification and cost estimation for all project cost items
Gives an understanding of the cost of implementing the project with different accuracy by the phase of the project
18
Cost breakdown structure
Cost control
Structures all project costs based on the work execution structure
Clearly defines the amount of costs for each type of work on the project
19
Cost control procedure, including invoicing and financial statements
Cost control
Defines the rules for controlling the expenditure of funds, including the disposal of savings and covering the deficit of funds
Gives the management a clear and understandable picture of the expenditure of funds on the project
20
Project organization chart
Human Resources management
Defines linear and functional relationships between project team personnel and linear functions
Allows you to fix positions and subordination within the team, distribute functions and determine the need for personnel involved in the project execution
21
Recruitment plan
Human Resources management
Provides information on recruitment methods and tools, as well as on the current recruitment status
Forms an understanding of what sources and when it is necessary to attract staff
22
Mobilization plan
Human Resources management
Determines the required mobilization for the project in the context of disciplines and the number of specialists
Provides an opportunity to predict and manage the mobilization of personnel for the successful implementation of the project
23
Matrix distribution of roles and responsibilities
Human Resources management
Distributes responsibility and authority within the team
Clearly defines who is responsible for what in the team
24
Project personnel training plan
Human Resources management
Creates a need for training of project team personnel
Forms the required plan for the development of the team's competencies
25
IT plan
Information management
Defines the landscape of the project and its implementation plan
Gives a clear understanding of who will perform the work in what software and how the landscape will be built
26
Project value improvement plan
Value improvement
Defines the methods required for the implementation of increasing the value of the project
Forms an understanding of which methods of increasing the value of the project (VIP) will be implemented and for what purpose
27
Register of lessons learned
Value improvement
Allows you to use previously accumulated and form new lessons learned
Gives confidence that the previously gained experience will be used on a new project, and the lessons learned from the new project will serve for future
28
Risk management plan Risk register
Risk management
Defines project risks, their assessment, and measures to minimize the likelihood of their occurrence and/or consequences
Allows you to control unforeseen expenses and the progress of the project as a whole
29
Quality management plan
Quality Management
Forms requirements for completeness, frequency, and areas of quality control of the project
Makes it possible to ensure the required quality of work and minimize the cost of correcting defects
30
Audit and inspection plan
Quality Management
Defines the list, frequency, and completeness of the checks carried out
Gives an understanding of the required budget, contracts, and measures to ensure the quality of work on the project
31
HSE plan
Health, industrial safety and environmental protection
Determine the procedure and those responsible for compliance with the requirements and the necessary measures
Minimizes the risks of accidents, accidents, and accidents during the implementation of the project
32
Permitting plan
Permissions and approvals
Determines the necessary approvals and permits during the implementation of the project
Gives a clear understanding of what, who, and when permissions and approvals should be obtained
33
Contract strategy
Contract management
Determines which contracts should be concluded within the framework of the project
Gives an understanding of the quantity and required quality of Contractors and Subcontractors
34
Contracting plan
Contract management
It is a list of all contracts on the project with the status of their conclusion and execution
Provides up-to-date information on the status of contracting and contract execution
35
Subcontracting Management Plan
Contract management
Defines the requirements for Subcontractors, the order of acceptance of their work, management, and control of work by third-party companies
Allows you to structure and organize work with subcontracting, the number of which on large projects is measured in dozens
36
Contractor lists
Contract management
Identifies all contractors and subcontractors on the project, including nominated ones, if necessary
Allows to limit the performance of work only by qualified performers, as well as the involvement of the required companies in the work
37
ITB (invitation to bid) package
Contract management
It consists of instructions, forms, and requirements for the formation of a TAP for participation in the competition
Enables all participants of the competition to prepare the most complete proposal on a single database of source data for the required forms
38
Procurement plan
Procurement and Logistics management
Defines requirements for the search for Suppliers, their selection, placing orders, and control of manufacturing
Allows to form clear requirements for the procurement and supply of equipment and materials
39
Logistics plan
Procurement and Logistics management
Defines the requirements for the transportation of materials and equipment at the stage from shipment to entrance control at the construction site
Allows to form clear requirements for the process of cargo transportation
40
Supplier selection procedure
Procurement and Logistics management
Contains clear requirements for selection, comparison of offers, and contracting with Suppliers
Gives a clear understanding of the process of choosing the best offer, including qualifications, technical and commercial parts of the TAP from Suppliers
41
Materials handling management plan
Materials handling management
It consists of the requirements and procedure for handling materials and equipment on-site at the storage stage before installation
Organizes the movement of thousands of items of materials and equipment on the site
42
Engineering management plan
Engineering management
Contains requirements for the performance of all engineering
Organizes all engineering works
43
List of documentation issued at each phase of the project in terms of engineering
Engineering management
It consists of all engineering documents, the development of which is required at each stage
Allows to clearly define the documents required for development, defining the requirements for documents, the necessary resources, and management tools
44
Early work plan
Construction management
Defines early work to optimize the timing of the project or to get an early return on investment
Allows to determine the early scope of work required for implementation, for example, to optimize the schedule by preparing the construction site before the conclusion of the main EPC contract
45
Construction Management Plan
Construction management
Defines the requirements for the organization, provision, execution, and delivery of construction works
Allows to form clear requirements for the SMR process on the site
46
Plan for simultaneous operations of several works (SimOps)
Construction management
It contains rules for performing several types of work in parallel, for instance: construction of the 2nd train of the plant and operation of the 1st train
Makes it possible to minimize the area of the object by performing SMR and operating objects in the immediate vicinity
47
System commissioning plan
Commissioning management
Describes the requirements for the commissioning of all systems of the facility
Allows to systematically and consistently launch all production systems in optimal time
48
Performance guaranty test plan
Commissioning management
It contains the requirements for warranty testing of technological installations of production
Makes it possible to fix the requirements and rules for confirming the main parameters of production